Current Road Projects

​​​​​​​​​​​​​​​​​​​​​​​​​​​​Projects under Construction

​​​​TO VIEW INTERACTIVE PROJECT MAP CLICK HERE


TAX 2014A PARKWAY BOULEVARD

The Tax 2014A Parkway Boulevard reconstruction contract was awarded to Tiseo Paving Company for a total contract amount of $7,426,912.50 in March of 2019. Construction activities consists of removal and replacement of pavement, water, sewer and storm lines from Heartz Road to Lodge Road and panel replacements from Denton Tap Road to MacArthur Road. Project also includes a 8 foot sidepath/trail on the north side of the road from Heartz Road to Moore Road and a 6 foot sidewalk along the south side of the roadway. Construction is anticipated to be completed in Spring of 2020.

Latest Update: 

Currently the contractor is constructing the west bound lanes (north lanes), 8 foot sidepath/trail, and installing conduits for light poles, light pole foundations and panels. Contractor is estimating to open all the four lanes for traffic by end of February 2020. The last phase of the project will include installing landscape features, panels and stamped concrete at intersections.

If you have any questions or concerns about the project, please contact: 
Kumar Gali, P.E., Assitant Director of Public Works - Engineering​ at 972-304-3679

ST 15-01A  FREEPORT PARKWAY, (BETHEL RD TO I-635)

The design contract for Freeport Parkway improvements was completed by J. Volk Consulting for a total contract amount of $726,000.  The project includes full pavement replacement, bridge reconstruction, utility replacement / rehabilitation, landscaping enhancement, geometry improvements, trail construction, lighting, and a new traffic signal. The construction project was awarded to Texas Sterling Construction Co. for a total contract amount of $16,519,808.64. Construction is anticipated to begin in Spring 2018.

Latest Update: ​

These lane closures will be in place for the duration of the Freeport Parkway Rehabilitation project, which is expected to take 18-24 months. The expected completion date for the project is Spring 2020.​

If you have questions or concerns about the project, please contact Kent Collins, P.E., Director of Public Works at 972-304-3679


PROJECTS IN DESIGN


TAX 2015B  PLANTATION DRIVE AND MOSSY OAKS STREET RECONSTRUCTION PROJECT 

The design for these improvements is currently underway with Pape-Dawson Engineers. The project will impact the entire length of Plantation Drive and Mossy Oaks Street. The project includes complete pavement reconstruction and utility upgrades. Construction is anticipated in FY 2020-2021.

If you have any questions or concerns about the project, please contact Jamie Brierton, Project Manager at 972-304-3679

TAX 2016B AIRLINE DRIVE 

A design contract for the reconstruction of Airline Drive was awarded to Kimley-Horn in summer 2017. The project consists of concrete replacement, utility upgrades and sidewalk improvements. The project will also improve drainage. Construction is anticipated to begin in 2020.

If you have any questions or concerns about the project, please contact Jamie Brierton, Project Manager at 972-304-3679

ST 16-01A S BELT LINE ROAD

A design contract for the reconstruction of S. Belt Line Road from Denton Tap Road to I-635 was awarded to Halff Associates, Inc. in the Spring of 2019. The project consists of paving, drainage, and utility improvements. Construction could start in the first half of 2021, pending funding availability.

If you have questions or concerns about the project, please contact Kent Collins, P.E., Director of Public Works at 972-304-3679

TAX 2017B OAK GROVE LANE
A design contract for the reconstruction of Oak Grove Lane was awarded to Pacheco Koch, LLC. in the Fall of 2018. The project consists of paving, drainage, sidewalk, and utility improvements. Construction is anticipated to begin in Winter of 2020.  

If you have any questions or concerns about the project, please contact Jamie Brierton, Project Manager at 972-304-3679

TAX 2017C CAMBRIA DRIVE AND WISE WAY
A design contract for the reconstruction of Cambria Drive and the Wise Way connection was awarded to Criado & Associates, Inc. in the Spring of 2019. The project consists of complete pavement reconstruction, utility upgrades, and storm drain improvements. Construction is anticipated to begin in 2021.​  

If you have any questions or concerns about the project, please contact Jamie Brierton, Project Manager at 972-304-3679​


FUTURE PROJECTS

SPANISH MOSS AND JEB COURT​
NEIGHBORHOOD ALLEY REPLACEMENT PROJECT #5
SOUTHWESTERN BLVD


Sidewalk repair process

1. DAMAGED SIDEWALK IS DEMOLISHED & REMOVED

2. GROUND IS COMPActED & PREPARED

3. WOOD FORMS ARE SET AND REBAR IS PLACED

4. CONCRETE IS POURED & CURES/DRIES TYPICALLY 24-72 HOURS

5. CONTROL JOINTS ARE SAWCUT AND SEALANT IS APPLIED TO EXPANSION JOINTS, IF ANY​