Construction Activity
Road Projects Under Construction
If you have any questions or concerns regarding a project, please contact Public Works Engineering, at 972-304-3679.
ST 16-01A S Belt Line Road
View the S Belt Line Reconstruction page for more information. Read through weekly project updates on the S Belt Line Reconstruction Updates page.
Canyon Drive Sidewalk Infill
This project was designed internally within the City of Coppell Public Works Department. C&J’s Designs and Solutions of East Texas, LLC will be infilling sidewalk along Canyon Drive from SH 121 Frontage Road to N Coppell Road. This project will increase accessibility in this area as well as account for the increased pedestrian traffic. Final inspections and payment application approvals are being scheduled now. The sidewalk infill at Canyon Drive began on Monday, October 9, 2023 and is anticipated to be completed in the Winter of 2023.
Maintenance Projects
Sidewalk Repair Process
- The damaged sidewalk is demolished and removed
- The ground is compacted and prepared
- Wood forms are set and rebar is placed
- Concrete is poured and cures/dries typically 24 to 72 hours
- Control joints are saw-cut and sealant is applied to expansion joints, if any
Projects in Design
Tax 2019C Woodhurst Drive
A design contract for the reconstruction of Woodhurst Drive was awarded to Westra Consultants in the Fall of 2020 in the amount of $359,500. The project consists of pavement reconstruction, utility upgrades, sidewalk improvements, and drainage improvements. Council approved construction costs of $4,843,494.15 awarded to Reliable Paving, Inc. The neighborhood meeting for this project will be on Wednesday, December 6, 2023. Construction start date COMING SOON! Visit the Woodhurst Drive Reconstruction page for more information.
S Moore Road Panel Replacement
F&F Concrete & LLC will replace roadway panels along S Moore Road from Shadowcrest Lane to E Bethel School Road. The panel replacements on this roadway will prolong the life of the road and ensure that it is easily drivable. This project will begin when funds are available or in the Summer of 2024 - whichever comes first.
Tax 2022A Royal Lane Reconstruction
A design contract for the reconstruction of Royal Lane was awarded to Teague, Nall, & Perkins in the Spring of 2022 in the amount of $1,403,000. The project consists of pavement reconstruction, utility upgrades, and sidewalk improvements. Construction is anticipated to begin in 2024.
Tax 2022B Bullock Drive & Howell Drive
A design contract for the reconstruction of Bullock Drive and Howell Drive was awarded to Pacheco Koch in the Fall of 2022 in the amount of $213,777.50. The project consists of pavement reconstruction, utility upgrades, sidewalk installation, and drainage improvements. Construction is anticipated to begin in 2024. Visit the Bullock and Howell Reconstruction page for more information.
Tax 2018A Spanish Moss Drive & Jeb Court
A design contract for the reconstruction of Spanish Moss Drive and Jeb Court was awarded to Huitt Zollars, Inc. in the Summer of 2019 in the amount of $200,295. The project consists of complete pavement reconstruction, utility upgrades, and sidewalk improvements. Construction is anticipated to begin in 2024.
Tax 2019B Southwestern Boulevard
A design contract for the reconstruction of Southwestern Blvd was awarded to Kirkman Engineering in the Fall of 2020 in the amount of $202,700. The project consists of pavement reconstruction, utility upgrades, sidewalk improvements, and drainage improvements. Construction is anticipated to begin in 2025.
Future Projects
Kaye Street Asphalt Overlay
Hillhaven Road, Woodway Drive, and Woodhill Complete Reconstruction
E Sandy Lake Road and Kimbel Kourt Sidewalk Infill
Park Projects Under Construction
Moore Road Elevated Boardwalk
A contract for the reconstruction of the Moore Road Boardwalk was awarded to Rebcon in November 2022. Work on the project began February 6, 2023. Included in the scope of project are a new boardwalk structure constructed along the south side of the pond and storm water improvements. Some nearby trails may be closed temporarily during the project. Construction is anticipated to be completed in Fall 2023.
The Duck Pond Park
A contract for the reconstruction of The Duck Pond Park was awarded to JB & Co., LLC in April 2023. Work on the project begins May 18, 2023. Park improvements included in the scope of the project include a new walking trail around the pond, pond edge reestablishment, retaining walls, concrete channel lining, playground surface replacement, drainage flume replacements, and landscape and irrigation improvements. For safety purposes the entirety of the park will be closed during construction. Construction is anticipated to be completed in Winter 2023.
Thweatt Park Pond/Erosion Project
A contract for the reconstruction of Thweatt Park was awarded to McMahon Contracting in February 2023. Work on the project will begin in June 2023. Included in the scope of the project are a new pond liner and repair erosion on the West side of the pond/park. For safety purposes the entirety of the park will be closed during construction. Construction is anticipated to be completed in Fall 2023.
Projects in Design
Magnolia Park Elevated Boardwalk
This project is in the design phase and continues to rest at 90% as we await the Archeological Survey results required by the United States Army Corps of Engineers (USACE). It is estimated that the survey process will be completed by late June 2023, at which time the City can proceed with finalizing a design and moving forward with a formal bid process.
Dog Park Reconstruction Project
This project is in the design phase and currently rests at 10%.