Current Road Projects

Projects Under Construction

If you have any questions or concerns regarding a project, please contact Public Works Engineering, at 972-304-3679.

ST 15-01A Freeport Parkway, (Bethel Road to I-635)

The design contract for Freeport Parkway improvements was completed by J. Volk Consulting for a total contract amount of $726,000. The project includes:

  • Bridge reconstruction
  • Full pavement replacement
  • Geometry improvements
  • Landscaping enhancement
  • Lighting
  • New traffic signal
  • Trail construction
  • Utility replacement/rehabilitation

Bid Awarded

The construction project was awarded to Texas Sterling Construction Co. for a total contract amount of $16,519,808.64. Construction is anticipated to begin in Spring 2020.

Latest Update

The contractor continues to work on the Freeport Parkway road construction of the southbound lanes between Bethel Road and Airline Road, bridge construction on the southbound lanes at Grapevine Creek, traffic signal work at the intersection of Southwestern Boulevard and Freeport Parkway, sidewalk and side path trail installations, and median work. There will be continuing lane closures on Freeport for the remaining work.

Tax 2016B Airline Drive

A design contract for the reconstruction of Airline Drive was awarded to Kimley-Horn in summer 2017. The project includes:

  • Concrete replacement
  • Utility upgrades
  • Sidewalk improvements
  • Drainage improvements 

Bid Awarded

The project was awarded to McMahon Contracting, LP for a total contract amount of $4,454,084.65.  Construction began Fall 2020 and is anticipated to be complete Winter 2021. 

Latest Update

The Pre-construction meeting was held on 09-17-20. The project started on 10-05-20. Traffic control has been set up and water line installations are in progress. Traffic has been shifted to westbound only until project completion.

Projects in Design

Tax 2015B Plantation Drive & Mossy Oaks Street Reconstruction Project

The design for these improvements is currently underway with Pape-Dawson Engineers. The project will impact the entire length of Plantation Drive and Mossy Oaks Street. The project includes complete pavement reconstruction and utility upgrades. Construction is anticipated to the Summer of 2021.

ST 16-01A S Belt Line Road

A design contract for the reconstruction of S Belt Line Road from Denton Tap Road to I-635 was awarded to Halff Associates, Inc. in the Spring of 2019. The project consists of paving, drainage, and utility improvements. Construction to begin in the Spring of 2021. 

Tax 2017C Cambria Drive & Wise Way

A design contract for the reconstruction of Cambria Drive and the Wise Way connection was awarded to Criado and Associates, Inc. in the Spring of 2019. The project consists of complete pavement reconstruction, utility upgrades, and storm drain improvements. Construction is anticipated to begin in 2021.

Tax 2018A Spanish Moss Drive & Jeb Court

A design contract for the reconstruction of Spanish Moss Drive and Jeb Court was awarded to Huitt Zollars, Inc. in the Summer of 2019. The project consists of complete pavement reconstruction, utility upgrades, and sidewalk improvements. Construction is anticipated to begin in 2023. 

Tax 2019B Southwestern Boulevard

A design contract for the reconstruction of Southwestern Blvd was awarded to Kirkman Engineering in the Fall of 2020 in the amount of $202,700. The project consists of pavement reconstruction, utility upgrades, sidewalk improvements, and drainage improvements. Construction is anticipated to begin in 2023. If you have any questions or concerns about the project, please contact Jamie Brierton, Project Manager, at 972-304-3679.

Tax 2019C Woodhurst Drive

A design contract for the reconstruction of Woodhurst Drive was awarded to Westra Consultants in the Fall of 2020 in the amount of $359,500. The project consists of pavement reconstruction, utility upgrades, sidewalk improvements, and drainage improvements. Construction is anticipated to begin in 2024.

Tax 2019A Neighborhood Alley Replacement Project #5

The City of Coppell designed plans for the reconstruction and replacement of the alleyways at Phillips Drive, Simmons Drive, and Oriole Lane/Villawood Lane. These projects consist of pavement reconstruction, utility upgrades, drainage improvements, and landscaping enhancements. Construction is to begin Spring 2021 and traffic control procedures will be in place for effective access to these neighborhoods. 

Future Projects


Sidewalk Repair Process

  1. The damaged sidewalk is demolished and removed
  2. The ground is compacted and prepared
  3. Wood forms are set and rebar is placed
  4. Concrete is poured and cures/dries typically 24 to 72 hours
  5. Control joints are saw-cut and sealant is applied to expansion joints, if any