Current Road Projects

Projects Under Construction

If you have any questions or concerns regarding a project, please contact Public Works Engineering, at 972-304-3679.

Tax 2016B Airline Drive

A design contract for the reconstruction of Airline Drive was awarded to Kimley-Horn in summer 2017. The project includes:

  • Concrete replacement
  • Utility upgrades
  • Sidewalk improvements
  • Drainage improvements 

Bid Awarded

The project was awarded to McMahon Contracting, LP for a total contract amount of $4,454,084.65.  Construction began Fall 2020 and is anticipated to be complete Winter 2021. 

Latest Update

The Pre-construction meeting was held on 09-17-20. The project started on 10-05-20. Traffic has been shifted to westbound only until project completion. Right now, traffic flow is in the southern lanes, and the southern right-of-way (ROW) sidewalk work is in progress.   

Tax 2017C Cambria Drive & Wise Way

A design contract for the reconstruction of Cambria Drive and the Wise Way connection was awarded to Criado and Associates, Inc. in the Spring of 2019. The project consists of:

  • Complete pavement reconstruction
  • Utility upgrades
  • Storm drain improvements

Bid Awarded

The project was awarded to Quality Excavation, LLC. for a total contract amount of $1,086,996. 

Latest Update

Pre-construction meeting was held on 03-30-2021. The project began the week of 04-19-2021 and will be limited to one-way traffic that is westbound for the duration of the project. Utility installations are in progress.

Tax 2019A Neighborhood Alley Replacement Project #5

The City of Coppell designed plans for the reconstruction and replacement of the alleyways at Phillips Drive, Simmons Drive, and Oriole Lane/Villawood Lane. These projects consist of:

  • Pavement reconstruction
  • Drainage improvements

Bid Awarded

The project was awarded to Advanced Contracting Group for a total contract amount of $899,025.

Latest Update

Pre-construction meeting was held on 04-08-2021. The project began the week of 04-19-2021. The order of re-constructing these alleys will be Simmons Drive, Oriole Lane/Villawood Lane, and then Phillips Drive.

Tax 2015B Plantation Drive & Mossy Oaks Street Reconstruction Project

A design contract for the reconstruction of Plantation Drive & Mossy Oaks Street was awarded to Pape-Dawson Engineers in the Winter of 2016. The project includes:

  • Complete pavement reconstruction
  • Utility upgrades
  • Sidewalk improvements

Bid Awarded

The project was awarded to DDM Construction Corp. for a total contract amount of $5,457,827.90

Latest Update

Pre-construction meeting was held on 06-03-2021. The project will begin on 06-21-2021.

Tax 2020 Denton Tap Road Intersection Improvements

A design contract for the reconstruction of four intersections along Denton Tap Road was awarded to Kimley-Horn in the Summer of 2019. Those four intersections are:  Parkway,  Southwestern,  Sandy Lake,  and  Bethel School. The project consists of:

  • Construction of turn lanes
  • Reconstruction of sidewalks and ramps
  • Traffic signal work

Bid Awarded

The project was awarded to Rebcon Inc. for a total contract amount of $2,777,148.70

Latest Update

Pre-construction meeting was held on 04-15-2021. The project began on 04-19-2021. The turn lane at Denton Tap/Southwestern is currently being worked on. Work will begin at Denton Tap/Parkway mid-summer of 2021. 


Projects in Design


ST 16-01A S Belt Line Road

A design contract for the reconstruction of S Belt Line Road from Denton Tap Road to I-635 was awarded to Halff Associates, Inc. in the Spring of 2019. The project consists of paving, drainage, and utility improvements. Construction to begin in the Summer of 2021. 

Tax 2018A Spanish Moss Drive & Jeb Court

A design contract for the reconstruction of Spanish Moss Drive and Jeb Court was awarded to Huitt Zollars, Inc. in the Summer of 2019. The project consists of complete pavement reconstruction, utility upgrades, and sidewalk improvements. Construction is anticipated to begin in 2023. 

Tax 2019B Southwestern Boulevard

A design contract for the reconstruction of Southwestern Blvd was awarded to Kirkman Engineering in the Fall of 2020 in the amount of $202,700. The project consists of pavement reconstruction, utility upgrades, sidewalk improvements, and drainage improvements. Construction is anticipated to begin in 2023.

Tax 2019C Woodhurst Drive

A design contract for the reconstruction of Woodhurst Drive was awarded to Westra Consultants in the Fall of 2020 in the amount of $359,500. The project consists of pavement reconstruction, utility upgrades, sidewalk improvements, and drainage improvements. Construction is anticipated to begin in 2024.

Future Projects

Tax 2021A Dividend Drive and Mockingbird Lane Panel Replacement Project


If you want to know more about Parks & Recreation projects going on in the city, please visit the City of Coppell Parks Projects page.

Sidewalk Repair Process

  1. The damaged sidewalk is demolished and removed
  2. The ground is compacted and prepared
  3. Wood forms are set and rebar is placed
  4. Concrete is poured and cures/dries typically 24 to 72 hours
  5. Control joints are saw-cut and sealant is applied to expansion joints, if any